| Action Date | Action Description |
|---|---|
| Aug 20, 2010 | Assent Application Received |
| Aug 23, 2010 | Administrative Review for Completeness |
| Aug 27, 2010 | Team Review for Completeness |
| Aug 27, 2010 | Team Review for Completeness |
| Aug 27, 2010 | Application Accepted |
| Aug 27, 2010 | Category B assigned |
| Aug 31, 2010 | Category A assigned |
| Aug 31, 2010 | 30 day Public Notice Issued |
| Sep 16, 2010 | HPHC Historical Preservation No Effect |
| Sep 30, 2010 | Public Notice End Date |
| Oct 22, 2010 | US Army Corp of Engineers Permit Date |
| Nov 15, 2010 | Dock Meeting -- Approval |
| Nov 15, 2010 | Biologist Report |
| Nov 15, 2010 | Engineering Report |
| Nov 15, 2010 | Dock/1.1.6 Review approval |
| Dec 03, 2010 | Typist for Processing |
| Dec 03, 2010 | Executive Sign Off |
| Dec 03, 2010 | Permit Approved |
| Dec 17, 2010 | Land Evidence Date |