| Action Date | Action Description |
|---|---|
| Dec 21, 2010 | Freshwater Wetland - Preliminary Determination |
| Dec 21, 2010 | Administrative Review for Completeness |
| Feb 04, 2011 | Application Accepted |
| Feb 11, 2011 | Team Review for Completeness |
| Feb 11, 2011 | Typist for Processing |
| Feb 11, 2011 | Permit Approved |
| Feb 14, 2011 | Executive Sign Off |
| Feb 14, 2011 | Sent to Photo Copy |
| Feb 16, 2011 | Land Evidence Date |
| Jun 28, 2011 | Modification Request |
| Jul 05, 2011 | Administrative Review for Completeness |
| Jul 07, 2011 | Team Review for Completeness |
| Jul 07, 2011 | Biologist Report |
| Jul 14, 2011 | Typist for Processing |
| Jul 14, 2011 | Modification Approved |
| Jul 15, 2011 | Executive Sign Off |
| Jul 15, 2011 | Sent to Photo Copy |
| Jul 18, 2011 | Land Evidence Date |
| Sep 30, 2011 | Modification Request |
| Oct 03, 2011 | Administrative Review for Completeness |
| Oct 14, 2011 | Team Review for Completeness |
| Oct 19, 2011 | Typist for Processing |
| Oct 19, 2011 | Sent to Photo Copy |
| Oct 20, 2011 | Executive Sign Off |
| Oct 20, 2011 | Land Evidence Date |
| Oct 20, 2011 | Biologist Report |
| Oct 21, 2011 | Modification Approved |