| Action Date | Action Description |
|---|---|
| Feb 18, 2011 | Assent Application Received |
| Feb 18, 2011 | Administrative Review for Completeness |
| Feb 23, 2011 | Team Review for Completeness |
| Feb 23, 2011 | Team Review for Completeness |
| Feb 23, 2011 | Application Accepted |
| Mar 09, 2011 | HPHC Historical Preservation No Effect |
| Apr 11, 2011 | Water Quality Certification |
| Apr 26, 2011 | Biologist Report |
| Apr 26, 2011 | Engineering Report |
| May 03, 2011 | Typist for Processing |
| May 03, 2011 | Permit Approved |
| May 03, 2011 | Executive Sign Off |
| May 03, 2011 | Sent to Photo Copy |
| May 05, 2011 | Land Evidence Date |
| Aug 10, 2011 | Commencement of Work Notice received |
| Mar 30, 2016 | Extension Toll letter mailed |