| Action Date | Action Description |
|---|---|
| May 24, 2011 | Assent Application Received |
| May 24, 2011 | Administrative Review for Completeness |
| Jun 22, 2011 | Team Review for Completeness |
| Jun 22, 2011 | Team Review for Completeness |
| Jun 22, 2011 | Application Accepted |
| Jul 12, 2011 | Additional Information Received |
| Jul 13, 2011 | HPHC Historical Preservation No Effect |
| Aug 05, 2011 | Typist for Processing |
| Aug 05, 2011 | Permit Approved |
| Aug 10, 2011 | Biologist Report |
| Aug 10, 2011 | Engineering Report |
| Aug 15, 2011 | Executive Sign Off |
| Aug 15, 2011 | Sent to Photo Copy |
| Sep 06, 2011 | Water Quality Certification |
| Oct 07, 2011 | Land Evidence Date |
| Jun 27, 2012 | Correspondence Received |
| Jun 28, 2012 | Correspondence Mailed/Faxed/E-mailed |