| Action Date | Action Description |
|---|---|
| Sep 01, 2011 | Assent Application Received |
| Sep 02, 2011 | Administrative Review for Completeness |
| Sep 06, 2011 | Team Review for Completeness |
| Sep 06, 2011 | Application Accepted |
| Oct 04, 2011 | 30 day Public Notice Issued |
| Oct 10, 2011 | HPHC Historical Preservation No Effect |
| Oct 25, 2011 | Correspondence Received |
| Nov 01, 2011 | Public Notice End Date Extension Granted |
| Nov 04, 2011 | Objections/Comments Received |
| Nov 04, 2011 | Objections/Comments Received |
| Nov 04, 2011 | Public Notice End Date |
| Nov 18, 2011 | Objections/Comments Received |
| Nov 18, 2011 | Public Notice End Date |
| Nov 22, 2011 | Objections/Comments Received |
| Dec 01, 2011 | Correspondence Mailed/Faxed/E-mailed |
| Dec 07, 2011 | Objections/Comments Received |
| Dec 08, 2011 | Objections/Comments Received |
| Dec 12, 2011 | Objections/Comments Received |
| Dec 12, 2011 | Objections/Comments Received |
| Dec 12, 2011 | Objections/Comments Received |
| Dec 12, 2011 | Objections/Comments Received |
| Dec 12, 2011 | Objections/Comments Received |
| Dec 13, 2011 | Objections/Comments Received |
| Dec 13, 2011 | Objections/Comments Received |
| Dec 13, 2011 | Objections/Comments Received |
| Dec 13, 2011 | Objections/Comments Received |
| Dec 14, 2011 | Objections/Comments Received |
| Dec 15, 2011 | Objections/Comments Received |
| Dec 15, 2011 | Objections/Comments Received |
| Dec 15, 2011 | Objections/Comments Received |
| Dec 19, 2011 | Objections/Comments Received |
| Dec 19, 2011 | Objections/Comments Received |
| Dec 20, 2011 | Objections/Comments Received |
| Dec 22, 2011 | Objections/Comments Received |
| Dec 27, 2011 | Objections/Comments Received |
| Jan 03, 2012 | Objections/Comments Received |
| Jan 09, 2012 | Objections/Comments Received |
| Jan 12, 2012 | Additional Information Received |
| Jan 13, 2012 | Objections/Comments Received |
| Jan 17, 2012 | Objections/Comments Received |
| Feb 14, 2012 | Additional Information Received |
| Feb 15, 2012 | Correspondence Mailed/Faxed/E-mailed |
| Feb 28, 2012 | Correspondence Received |
| Mar 05, 2012 | Correspondence Received |
| Mar 15, 2012 | Correspondence Received |
| Mar 16, 2012 | Biologist Report |
| Mar 16, 2012 | Geologist Report |
| Mar 16, 2012 | Engineering Report |
| Mar 16, 2012 | Mail Agenda Notice |
| Mar 28, 2012 | Additional Information Requested from Applicant |
| Apr 04, 2012 | Correspondence Received |
| Apr 04, 2012 | Correspondence Received |
| Apr 04, 2012 | Correspondence Received |
| Apr 04, 2012 | Correspondence Received |
| Apr 05, 2012 | Correspondence Received |
| Apr 10, 2012 | Council Decision - Denied |
| Apr 10, 2012 | Semi-Monthly Meeting Date Scheduled |
| Apr 13, 2012 | Objections/Comments Received |
| Apr 24, 2012 | Semi-Monthly Meeting Held |
| Apr 30, 2012 | Mail Agenda Notice |
| May 08, 2012 | Council Approval Granted |
| May 08, 2012 | Semi-Monthly Meeting Date Scheduled |
| May 08, 2012 | Semi-Monthly Meeting Held |
| May 22, 2012 | Correspondence Received |
| Jun 18, 2012 | Correspondence Received |
| Jun 21, 2012 | US Army Corps of Engineers Approval Received |
| Jun 26, 2012 | Legal Response/Decision |
| Jun 26, 2012 | Under Review/Decision |
| Jun 27, 2012 | 30 Day Appeal Notification to Owner |
| Jul 05, 2012 | Additional Information Received |
| Jul 17, 2012 | Typist for Processing |
| Jul 17, 2012 | Executive Sign Off |
| Jul 17, 2012 | Sent to Photo Copy |
| Jul 17, 2012 | Permit Approved |
| Jul 17, 2012 | Stipulation Package by Engineer |
| Jul 31, 2012 | Correspondence Received |
| Aug 21, 2012 | Correspondence Mailed/Faxed/E-mailed |
| Aug 24, 2012 | Correspondence Received |
| Sep 18, 2012 | Typist for Processing |
| Sep 18, 2012 | Modification Approved |
| Sep 19, 2012 | Executive Sign Off |
| Sep 19, 2012 | Sent to Photo Copy |
| Sep 24, 2012 | Land Evidence Date |
| Oct 04, 2012 | Land Evidence Date |
| Nov 12, 2013 | Correspondence Received |
| Mar 20, 2014 | Correspondence Received |
| May 30, 2014 | Mail Agenda Notice |
| Jun 17, 2014 | Entry of Appearance Received |
| Jun 18, 2014 | Correspondence Received |
| Jun 18, 2014 | Correspondence Received |
| Jun 19, 2014 | Objections/Comments Received |
| Jun 24, 2014 | Semi-Monthly Meeting Held |
| Jun 24, 2014 | Objections/Comments Received |
| Jun 24, 2014 | Semi-Monthly Meeting Date Scheduled |
| Aug 05, 2014 | Objections/Comments Received |
| Sep 09, 2014 | Legal Response/Decision |
| Sep 09, 2014 | 30 Day Appeal Notification to Owner |
| Apr 14, 2016 | Extension of Permit Request |
| Mar 01, 2017 | Correspondence Received |
| May 04, 2017 | Modification Request |
| May 04, 2017 | Administrative Review for Completeness |
| May 09, 2017 | Additional Information Received |
| May 11, 2017 | Additional Information Received |
| May 11, 2017 | Application Accepted |
| May 11, 2017 | Team Review for Completeness |
| May 15, 2017 | Typist for Processing |
| May 15, 2017 | Executive Sign Off |
| May 15, 2017 | Sent to Photo Copy |
| May 15, 2017 | Modification Approved |
| May 18, 2017 | Land Evidence Date |
| Jan 30, 2018 | Modification Amended |
| Feb 13, 2018 | Assent Correction Mailed |
| Feb 20, 2018 | Land Evidence Date |
| May 22, 2020 | Additional Information Received |
| Jun 20, 2022 | Letter of Authorization |