| Action Date | Action Description |
|---|---|
| Sep 21, 2011 | Assent Application Received |
| Sep 21, 2011 | Administrative Review for Completeness |
| Sep 26, 2011 | Team Review for Completeness |
| Sep 26, 2011 | Team Review for Completeness |
| Sep 26, 2011 | Application Accepted |
| Oct 04, 2011 | Additional Information Requested from Applicant |
| Nov 16, 2011 | HPHC Historical Preservation No Effect |
| Nov 18, 2011 | Additional Information Received |
| Dec 06, 2011 | Biologist Report |
| Dec 07, 2011 | Engineering Report |
| Dec 08, 2011 | Typist for Processing |
| Dec 08, 2011 | Executive Sign Off |
| Dec 08, 2011 | Sent to Photo Copy |
| Dec 08, 2011 | Permit Approved |
| Feb 14, 2012 | Land Evidence Date |