| Action Date | Action Description |
|---|---|
| Oct 26, 2011 | Assent Application Received |
| Oct 26, 2011 | Administrative Review for Completeness |
| Oct 31, 2011 | Team Review for Completeness |
| Oct 31, 2011 | Team Review for Completeness |
| Oct 31, 2011 | Application Accepted |
| Dec 13, 2011 | HPHC Historical Preservation No Effect |
| Dec 19, 2011 | Additional Information Received |
| Dec 28, 2011 | Additional Information Received |
| Jan 27, 2012 | Additional Information Received |
| Feb 14, 2012 | Engineering Report |
| Feb 14, 2012 | Biologist Report |
| Feb 15, 2012 | Typist for Processing |
| Feb 15, 2012 | Permit Approved |
| Feb 16, 2012 | Executive Sign Off |
| Feb 16, 2012 | Sent to Photo Copy |
| Feb 28, 2012 | Land Evidence Date |