| Action Date | Action Description |
|---|---|
| Oct 28, 2011 | Assent Application Received |
| Oct 31, 2011 | Administrative Review for Completeness |
| Oct 31, 2011 | Additional Information Received |
| Nov 01, 2011 | Team Review for Completeness |
| Nov 02, 2011 | Team Review for Completeness |
| Nov 02, 2011 | Application Accepted |
| Nov 02, 2011 | Biologist Report |
| Nov 02, 2011 | Engineering Report |
| Nov 03, 2011 | Typist for Processing |
| Nov 03, 2011 | Executive Sign Off |
| Nov 03, 2011 | Sent to Photo Copy |
| Nov 03, 2011 | Permit Approved |
| Nov 23, 2011 | HPHC Historical Preservation No Effect |
| Feb 06, 2012 | Land Evidence Date |