| Action Date | Action Description |
|---|---|
| Nov 02, 2011 | Assent Application Received |
| Nov 03, 2011 | Administrative Review for Completeness |
| Nov 14, 2011 | Team Review for Completeness |
| Nov 14, 2011 | Team Review for Completeness |
| Nov 14, 2011 | Deficient Application - Owner Notification Sent |
| Dec 05, 2011 | Deficient Application Picked Up |
| Jul 02, 2012 | Deficiency Response Received |
| Jul 09, 2012 | Team Review for Completeness |
| Jul 09, 2012 | Team Review for Completeness |
| Jul 09, 2012 | Application Accepted |
| Jul 13, 2012 | Biologist Report |
| Jul 13, 2012 | Engineering Report |
| Jul 16, 2012 | Typist for Processing |
| Jul 16, 2012 | Permit Approved |
| Jul 16, 2012 | Pre-construction requirement by CRMC staff |
| Jul 17, 2012 | Executive Sign Off |
| Jul 17, 2012 | Sent to Photo Copy |
| Jul 20, 2012 | Land Evidence Date |
| Aug 10, 2012 | Commencement of Work Notice received |