| Action Date | Action Description |
|---|---|
| May 07, 2012 | Assent Application Received |
| May 07, 2012 | Administrative Review for Completeness |
| May 10, 2012 | Team Review for Completeness |
| May 10, 2012 | Team Review for Completeness |
| May 10, 2012 | Application Accepted |
| May 18, 2012 | 30 day Public Notice Issued |
| May 22, 2012 | HPHC Historical Preservation No Effect |
| Jun 06, 2012 | Correspondence Received |
| Jun 18, 2012 | Public Notice End Date |
| Jun 27, 2012 | Biologist Report |
| Jun 27, 2012 | Mail Agenda Notice |
| Jun 27, 2012 | Correspondence Received |
| Jun 27, 2012 | US Army Corps of Engineers Approval Received |
| Jul 02, 2012 | Public Notice End Date Extension Granted |
| Jul 03, 2012 | Engineering Report |
| Jul 24, 2012 | Council Approval Granted |
| Jul 24, 2012 | Semi-Monthly Meeting Held |
| Jul 24, 2012 | Semi-Monthly Meeting Date Scheduled |
| Aug 01, 2012 | Stipulation Package from Biologist |
| Aug 01, 2012 | Stipulation Package by Engineer |
| Aug 02, 2012 | Legal Response/Decision |
| Aug 06, 2012 | Typist for Processing |
| Aug 06, 2012 | Executive Sign Off |
| Aug 06, 2012 | Sent to Photo Copy |
| Aug 06, 2012 | Permit Approved |
| Aug 22, 2012 | Land Evidence Date |