| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Aug 21, 2012 | Assent Application Received |
| Aug 22, 2012 | Administrative Review for Completeness |
| Aug 28, 2012 | Team Review for Completeness |
| Aug 28, 2012 | Application Accepted |
| Sep 12, 2012 | HPHC Historical Preservation No Effect |
| Nov 07, 2012 | Additional Information Received |
| Nov 26, 2012 | 30 day Public Notice Issued |
| Dec 26, 2012 | Public Notice End Date |
| Jan 18, 2013 | Category B assigned |
| Feb 04, 2013 | Biologist Report |
| Feb 08, 2013 | US Army Corps of Engineers Approval Received |
| Feb 15, 2013 | Typist for Processing |
| Feb 15, 2013 | Permit Approved |
| Feb 19, 2013 | Executive Sign Off |
| Feb 19, 2013 | Sent to Photo Copy |
| Feb 26, 2013 | Land Evidence Date |
| Jul 06, 2017 | Expiration of Assent/End of Tolling Legislation |
| Dec 19, 2017 | Modification Request |
| Dec 20, 2017 | Administrative Review for Completeness |
| Dec 20, 2017 | Team Review for Completeness |
| Dec 20, 2017 | Application Accepted |
| Jan 26, 2018 | HPHC Historical Preservation No Effect |
| Feb 14, 2018 | Biologist Report |
| Feb 14, 2018 | Modification Approved |
| Feb 28, 2018 | Land Evidence Date |