| Action Date | Action Description |
|---|---|
| Sep 17, 2012 | Assent Application Received |
| Sep 17, 2012 | Administrative Review for Completeness |
| Sep 18, 2012 | Team Review for Completeness |
| Sep 18, 2012 | Team Review for Completeness |
| Sep 18, 2012 | Application Accepted |
| Sep 27, 2012 | HPHC Historical Preservation No Effect |
| Nov 20, 2012 | Additional Information Received |
| Dec 03, 2012 | Additional Information Received |
| Jan 09, 2013 | Additional Information Received |
| Jan 10, 2013 | Water Quality Certification |
| Jan 10, 2013 | Water Quality Certification |
| Jan 29, 2013 | Biologist Report |
| Jan 29, 2013 | Engineering Report |
| Jan 30, 2013 | Typist for Processing |
| Jan 30, 2013 | Executive Sign Off |
| Jan 30, 2013 | Permit Approved |
| Jan 31, 2013 | Sent to Photo Copy |
| Mar 08, 2013 | Land Evidence Date |
| Jan 16, 2014 | Modification Request |
| Jan 17, 2014 | Administrative Review for Completeness |
| Jan 23, 2014 | Application Accepted |
| Jan 28, 2014 | Team Review for Completeness |
| Jan 28, 2014 | Team Review for Completeness |
| Feb 17, 2014 | Engineering Report |
| Feb 18, 2014 | Typist for Processing |
| Feb 18, 2014 | Modification Approved |
| Feb 19, 2014 | Executive Sign Off |
| Feb 19, 2014 | Sent to Photo Copy |
| Feb 24, 2014 | Land Evidence Date |
| Feb 25, 2014 | HPHC Historical Preservation No Effect |
| Apr 09, 2014 | Commencement of Work Notice received |