| Action Date | Action Description |
|---|---|
| Mar 08, 2013 | Assent Application Received |
| Mar 11, 2013 | Administrative Review for Completeness |
| Mar 26, 2013 | Team Review for Completeness |
| Mar 26, 2013 | Team Review for Completeness |
| Mar 26, 2013 | Application Accepted |
| Apr 02, 2013 | 30 day Public Notice Issued |
| Apr 02, 2013 | Public Notice End Date |
| May 06, 2013 | HPHC Historical Preservation No Effect |
| May 21, 2013 | Biologist Report |
| May 21, 2013 | Engineering Report |
| May 22, 2013 | Mail Agenda Notice |
| May 23, 2013 | Engineering Report |
| May 24, 2013 | US Army Corps of Engineers Approval Received |
| May 28, 2013 | Council Approval Granted |
| May 28, 2013 | Semi-Monthly Meeting Date Scheduled |
| May 28, 2013 | Semi-Monthly Meeting Held |
| May 30, 2013 | Stipulation Package from Biologist |
| May 30, 2013 | Stipulation Package by Engineer |
| Jun 25, 2013 | Legal Response/Decision |
| Jun 25, 2013 | Under Review/Decision |
| Jun 25, 2013 | 30 Day Appeal Notification to Owner |
| Jul 12, 2013 | Typist for Processing |
| Jul 12, 2013 | Permit Approved |
| Jul 15, 2013 | Executive Sign Off |
| Jul 15, 2013 | Sent to Photo Copy |
| Apr 09, 2014 | Pre-construction requirement by CRMC staff |
| Apr 09, 2014 | Commencement of Work Notice received |