| Action Date | Action Description |
|---|---|
| Jul 26, 2013 | Assent Application Received |
| Jul 31, 2013 | Administrative Review for Completeness |
| Aug 06, 2013 | Team Review for Completeness |
| Aug 06, 2013 | Application Accepted |
| Aug 14, 2013 | Category A* (Docks) |
| Aug 26, 2013 | HPHC Historical Preservation No Effect |
| Sep 24, 2013 | 30 day Public Notice Issued |
| Oct 04, 2013 | Objections/Comments Received |
| Oct 23, 2013 | Public Notice End Date |
| Jan 13, 2014 | Objection withdrawal received |
| Jan 13, 2014 | Plans Received |
| Jan 16, 2014 | Plans Received |
| Feb 26, 2014 | Biologist Report |
| Feb 28, 2014 | Typist for Processing |
| Feb 28, 2014 | Executive Sign Off |
| Feb 28, 2014 | Sent to Photo Copy |
| Feb 28, 2014 | Permit Approved |
| Mar 04, 2014 | Land Evidence Date |
| Mar 06, 2014 | US Army Corps of Engineers Approval Received |