| Action Date | Action Description |
|---|---|
| Apr 10, 2015 | Assent Application Received |
| Apr 13, 2015 | Administrative Review for Completeness |
| Apr 13, 2015 | Team Review for Completeness |
| Apr 16, 2015 | Application Accepted |
| Apr 16, 2015 | Engineering Report |
| Apr 20, 2015 | 30 day Public Notice Issued |
| May 05, 2015 | Public Notice End Date |
| Jun 09, 2015 | HPHC Historical Preservation No Effect |
| Aug 03, 2015 | Biologist Report |
| Sep 03, 2015 | Plans Received |
| Sep 04, 2015 | Plans Received |
| Sep 11, 2015 | Typist for Processing |
| Sep 14, 2015 | Executive Sign Off |
| Sep 14, 2015 | Sent to Photo Copy |
| Sep 14, 2015 | Permit Approved |
| Sep 16, 2015 | Land Evidence Date |
| Sep 21, 2015 | Water Quality Certification |