| Action Date | Action Description |
|---|---|
| Feb 15, 2016 | Application Accepted |
| Feb 15, 2016 | Assent Application Received |
| Feb 15, 2016 | Administrative Review for Completeness |
| Feb 15, 2016 | Team Review for Completeness |
| Mar 04, 2016 | Biologist Report |
| Mar 07, 2016 | Typist for Processing |
| Mar 07, 2016 | Executive Sign Off |
| Mar 07, 2016 | Sent to Photo Copy |
| Mar 07, 2016 | Permit Approved |
| Mar 07, 2016 | Land Evidence Date |
| Mar 18, 2016 | HPHC Historical Preservation No Effect |
| May 14, 2019 | Extension of Permit Request |
| May 15, 2019 | Enforcement Compliance Inspection Required |
| May 16, 2019 | Process Extension |
| May 16, 2019 | Extension Approved |
| Apr 24, 2020 | Extension of Permit Request |
| Apr 30, 2020 | Enforcement Compliance Inspection Required |
| Apr 30, 2020 | Process Extension |
| Apr 30, 2020 | Extension Approved |
| Jan 12, 2021 | Modification Request |
| Jan 13, 2021 | Administrative Review for Completeness |
| Jan 21, 2021 | Bio Team Review for Completeness |
| Jan 21, 2021 | Project Manager |
| Feb 17, 2021 | HPHC Historical Preservation No Effect |
| Feb 17, 2021 | HPHC Review Pending |
| Feb 26, 2021 | Plans Received |
| Mar 17, 2021 | Biologist Report |
| Mar 17, 2021 | Stipulation Package from Biologist |
| Mar 18, 2021 | Typist for Processing |
| Mar 18, 2021 | Executive Sign Off |
| Mar 18, 2021 | Sent to Photo Copy |
| Mar 18, 2021 | Modification Approved |
| Mar 29, 2021 | Land Evidence Date |