| Action Date | Action Description |
|---|---|
| Oct 21, 2016 | Freshwater Wetland - Preliminary Determination |
| Oct 24, 2016 | Administrative Review for Completeness |
| Oct 25, 2016 | Team Review for Completeness |
| Oct 25, 2016 | Application Accepted |
| Nov 10, 2016 | HPHC Historical Preservation No Effect |
| Nov 18, 2016 | Biologist Report |
| Nov 18, 2016 | Typist for Processing |
| Nov 23, 2016 | Executive Sign Off |
| Nov 23, 2016 | Sent to Photo Copy |
| Nov 23, 2016 | Permit Approved |
| Mar 24, 2017 | Duplicate Original Assent requested/mailed |
| Apr 12, 2017 | Land Evidence Date |
| May 16, 2017 | Modification Request |
| May 18, 2017 | Administrative Review for Completeness |
| May 18, 2017 | Team Review for Completeness |
| May 18, 2017 | Application Accepted |
| Jun 05, 2017 | HPHC Historical Preservation No Effect |
| Jun 08, 2017 | Biologist Report |
| Jun 12, 2017 | Typist for Processing |
| Jun 12, 2017 | Executive Sign Off |
| Jun 12, 2017 | Sent to Photo Copy |
| Jun 12, 2017 | Modification Approved |
| Jul 03, 2017 | Land Evidence Date |