| Action Date | Action Description |
|---|---|
| Dec 05, 2016 | Assent Application Received |
| Dec 07, 2016 | Administrative Review for Completeness |
| Dec 08, 2016 | Team Review for Completeness |
| Dec 08, 2016 | Team Review for Completeness |
| Dec 08, 2016 | Application Accepted |
| Dec 19, 2016 | HPHC Historical Preservation No Effect |
| Feb 23, 2017 | Plans Received |
| Feb 24, 2017 | Typist for Processing |
| Feb 24, 2017 | Executive Sign Off |
| Feb 24, 2017 | Sent to Photo Copy |
| Feb 24, 2017 | Permit Approved |
| Feb 24, 2017 | Biologist Report |
| Feb 24, 2017 | Engineering Report |
| Mar 01, 2017 | Assent Correction Mailed |
| Mar 10, 2017 | Land Evidence Date |
| Sep 21, 2017 | Commencement of Work Notice received |