| Action Date | Action Description |
|---|---|
| Aug 28, 2017 | Assent Application Received |
| Aug 28, 2017 | Administrative Review for Completeness |
| Sep 12, 2017 | Team Review for Completeness |
| Sep 12, 2017 | Application Accepted |
| Sep 26, 2017 | HPHC Historical Preservation No Effect |
| Oct 10, 2017 | Biologist Report |
| Oct 12, 2017 | Typist for Processing |
| Oct 12, 2017 | Executive Sign Off |
| Oct 12, 2017 | Sent to Photo Copy |
| Oct 12, 2017 | Permit Approved |
| Nov 02, 2017 | Land Evidence Date |
| Sep 13, 2018 | Modification Request |
| Sep 13, 2018 | Administrative Review for Completeness |
| Sep 17, 2018 | Team Review for Completeness |
| Sep 17, 2018 | Application Accepted |
| Oct 02, 2018 | HPHC Historical Preservation No Effect |
| Oct 30, 2018 | Additional Information Requested from Applicant |
| Nov 02, 2018 | Additional Information Received |
| Nov 13, 2018 | Modification Approved |
| Nov 13, 2018 | Biologist Report |
| Dec 03, 2018 | Land Evidence Date |