| Action Date | Action Description |
|---|---|
| Mar 05, 2018 | Assent Application Received |
| Mar 05, 2018 | Administrative Review for Completeness |
| Mar 09, 2018 | Team Review for Completeness |
| Mar 09, 2018 | Application Accepted |
| Mar 20, 2018 | HPHC Historical Preservation No Effect |
| May 04, 2018 | Plans Received |
| May 09, 2018 | Biologist Report |
| May 10, 2018 | Typist for Processing |
| May 10, 2018 | Executive Sign Off |
| May 10, 2018 | Sent to Photo Copy |
| May 10, 2018 | Permit Approved |
| May 21, 2018 | Land Evidence Date |
| Oct 16, 2020 | Extension of Permit Request |
| Mar 16, 2021 | Enforcement Compliance Inspection Required |
| Mar 17, 2021 | Process Extension |
| Mar 17, 2021 | Extension Approved |
| Aug 02, 2021 | Modification Request |
| Aug 05, 2021 | Administrative Review for Completeness |
| Aug 17, 2021 | Project Manager |
| Aug 17, 2021 | Bio Team Review for Completeness |
| Sep 03, 2021 | HPHC Historical Preservation No Effect |
| Sep 03, 2021 | HPHC Review Pending |
| Sep 17, 2021 | Stipulation Package from Biologist |
| Sep 17, 2021 | Biologist Report |
| Sep 21, 2021 | Typist for Processing |
| Sep 21, 2021 | Executive Sign Off |
| Sep 21, 2021 | Sent to Photo Copy |
| Sep 21, 2021 | Modification Approved |
| Sep 29, 2021 | Assent Requirement |
| Oct 22, 2021 | Land Evidence Date |
| Mar 10, 2022 | Extension of Permit Request |
| Mar 14, 2022 | Enforcement Compliance Inspection Required |
| Mar 25, 2022 | Extension Approved |