| Action Date | Action Description |
|---|---|
| Apr 09, 2018 | Assent Application Received |
| Apr 12, 2018 | Administrative Review for Completeness |
| Apr 12, 2018 | Correspondence Received |
| May 21, 2018 | Correspondence Received |
| May 25, 2018 | Application Accepted |
| May 25, 2018 | Team Review for Completeness |
| May 25, 2018 | Team Review for Completeness |
| Jun 01, 2018 | Correspondence Received |
| Jun 12, 2018 | HPHC Historical Preservation No Effect |
| Dec 26, 2018 | Additional Information Received |
| Apr 02, 2019 | Additional Information Received |
| Jul 16, 2019 | Typist for Processing |
| Jul 16, 2019 | Executive Sign Off |
| Jul 16, 2019 | Sent to Photo Copy |
| Jul 16, 2019 | Permit Approved |
| Jul 16, 2019 | Biologist Report |
| Jul 16, 2019 | Engineering Report |
| Aug 08, 2019 | Land Evidence Date |