| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| May 23, 2018 | Assent Application Received |
| May 23, 2018 | Administrative Review for Completeness |
| May 31, 2018 | Team Review for Completeness |
| May 31, 2018 | Application Accepted |
| Jun 12, 2018 | HPHC Historical Preservation No Effect |
| Jun 14, 2018 | 30 day Public Notice Issued |
| Jul 09, 2018 | Objections/Comments Received |
| Jul 14, 2018 | Public Notice End Date |
| Aug 07, 2018 | Correspondence Received |
| Oct 05, 2018 | Engineering Report |
| Oct 24, 2018 | Supervisor Biologist SignOff |
| Oct 24, 2018 | Supervisor Engineer SignOff |
| Oct 25, 2018 | Executive Signoff of Staff Reports |
| Oct 25, 2018 | Mail Agenda Notice |
| Nov 13, 2018 | Council Approval Granted |
| Nov 13, 2018 | Semi-Monthly Meeting Date Scheduled |
| Nov 19, 2018 | Legal Response/Decision |
| Nov 29, 2018 | Typist for Processing |
| Nov 29, 2018 | Executive Sign Off |
| Nov 29, 2018 | Sent to Photo Copy |
| Nov 29, 2018 | Permit Approved |
| Nov 29, 2018 | Stipulation Package by Engineer |
| Dec 05, 2018 | Land Evidence Date |