| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Dec 10, 2018 | Assent Application Received |
| Dec 10, 2018 | HPHC Review Pending |
| Dec 10, 2018 | Team Review for Completeness |
| Dec 10, 2018 | Application Accepted |
| Dec 10, 2018 | Administrative Review for Completeness |
| Jan 02, 2019 | 30 day Public Notice Issued |
| Jan 07, 2019 | HPHC Historical Preservation No Effect |
| Feb 02, 2019 | Public Notice End Date |
| Feb 05, 2019 | Dock/1.1.6 Review approval |
| Mar 07, 2019 | Additional Information Received |
| Apr 05, 2019 | Dock/1.1.6 Review approval |
| Apr 09, 2019 | Biologist Report |
| Apr 09, 2019 | Engineering Report |
| Apr 11, 2019 | Typist for Processing |
| Apr 11, 2019 | Executive Sign Off |
| Apr 11, 2019 | Sent to Photo Copy |
| Apr 11, 2019 | Permit Approved |
| May 14, 2019 | Land Evidence Date |
| Jan 29, 2024 | Modification Request |
| Feb 05, 2024 | Administrative Review for Completeness |
| Feb 09, 2024 | Bio Team Review for Completeness |
| Feb 09, 2024 | Project Manager |
| Feb 09, 2024 | Application Accepted |
| Feb 09, 2024 | Project Manager |
| Mar 08, 2024 | HPHC Historical Preservation No Effect |
| Mar 14, 2024 | 30 day Public Notice Issued |
| Apr 14, 2024 | Public Notice End Date |
| May 10, 2024 | Dock/1.1.6 Review approval |
| May 14, 2024 | Biologist Report |
| May 28, 2024 | Typist for Processing |
| May 28, 2024 | Modification Approved |