| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Land Evidence Date | |
| Dec 31, 2018 | Assent Application Received |
| Dec 31, 2018 | Administrative Review for Completeness |
| Jan 09, 2019 | Team Review for Completeness |
| Jan 09, 2019 | Deficient Application - Owner Notification Sent |
| Jan 23, 2019 | Deficient Application Picked Up |
| Apr 29, 2019 | Deficiency Response Received |
| Apr 30, 2019 | Team Review for Completeness |
| Apr 30, 2019 | Application Accepted |
| May 10, 2019 | HPHC Review Pending |
| May 10, 2019 | HPHC Historical Preservation No Effect |
| May 28, 2019 | 30 day Public Notice Issued |
| Jun 28, 2019 | Public Notice End Date |
| Aug 02, 2019 | Dock/1.1.6 Review approval |
| Sep 17, 2019 | Typist for Processing |
| Sep 17, 2019 | Executive Sign Off |
| Sep 17, 2019 | Sent to Photo Copy |
| Sep 17, 2019 | Permit Approved |
| Sep 17, 2019 | Biologist Report |
| Sep 17, 2019 | Engineering Report |
| Oct 02, 2019 | Land Evidence Date |
| Jun 03, 2024 | Modification Request |
| Jun 10, 2024 | Administrative Review for Completeness |
| Jun 12, 2024 | Bio Team Review for Completeness |
| Jun 26, 2024 | Deficient Application - Owner Notification Sent |
| Jun 26, 2024 | Eng Team Review for Completeness |
| Jul 05, 2024 | Deficiency Response Received |
| Nov 08, 2024 | Eng Team Review for Completeness |
| Nov 08, 2024 | Application Accepted |
| Nov 19, 2024 | HPHC Historical Preservation No Effect |
| Nov 29, 2024 | 30 day Public Notice Issued |
| Dec 29, 2024 | Public Notice End Date |
| Feb 28, 2025 | Typist for Processing |
| Feb 28, 2025 | Executive Sign Off |
| Feb 28, 2025 | Sent to Photo Copy |
| Feb 28, 2025 | Modification Approved |
| Feb 28, 2025 | Modification mailed |
| Feb 28, 2025 | Engineering Report |
| Mar 06, 2025 | Permit Mailed |