| Action Date | Action Description |
|---|---|
| Jan 25, 2019 | Assent Application Received |
| Jan 25, 2019 | Administrative Review for Completeness |
| Jan 25, 2019 | Team Review for Completeness |
| Jan 25, 2019 | Category A* (Docks) |
| Jan 28, 2019 | Application Accepted |
| Jan 30, 2019 | 30 day Public Notice Issued |
| Feb 14, 2019 | HPHC Review Pending |
| Feb 14, 2019 | HPHC Historical Preservation No Effect |
| Mar 01, 2019 | Public Notice End Date |
| May 20, 2019 | Plans Received |
| Jun 07, 2019 | Biologist Report |
| Jun 11, 2019 | Supervisor Biologist SignOff |
| Jun 11, 2019 | Supervisor Engineer SignOff |
| Jun 11, 2019 | Executive Signoff of Staff Reports |
| Jul 11, 2019 | Ready to Schedule Semi-Monthly Meeting |
| Jul 11, 2019 | Mail Agenda Notice |
| Jul 23, 2019 | Council Approval Granted |
| Jul 23, 2019 | Semi-Monthly Meeting Date Scheduled |
| Aug 02, 2019 | Legal Response/Decision |
| Aug 02, 2019 | 30 Day Appeal Notification to Owner |
| Aug 13, 2019 | Plans Received |
| Aug 15, 2019 | Stipulation Package from Biologist |
| Aug 16, 2019 | Typist for Processing |
| Aug 16, 2019 | Executive Sign Off |
| Aug 16, 2019 | Sent to Photo Copy |
| Aug 16, 2019 | Permit Approved |
| Sep 09, 2019 | Land Evidence Date |
| Nov 05, 2019 | Assent Requirement |