| Action Date | Action Description |
|---|---|
| Jan 31, 2019 | Assent Application Received |
| Jan 31, 2019 | Administrative Review for Completeness |
| Feb 01, 2019 | Team Review for Completeness |
| Feb 01, 2019 | Application Accepted |
| Feb 20, 2019 | HPHC Review Pending |
| Feb 20, 2019 | HPHC Historical Preservation No Effect |
| Mar 25, 2019 | Additional Information Received |
| Apr 22, 2019 | Additional Information Received |
| Apr 23, 2019 | Typist for Processing |
| Apr 23, 2019 | Executive Sign Off |
| Apr 23, 2019 | Sent to Photo Copy |
| Apr 23, 2019 | Permit Approved |
| Apr 23, 2019 | Biologist Report |