| Action Date | Action Description |
|---|---|
| Mar 07, 2019 | Assent Application Received |
| Mar 11, 2019 | Administrative Review for Completeness |
| Mar 11, 2019 | Team Review for Completeness |
| Mar 11, 2019 | Application Accepted |
| Mar 14, 2019 | Additional Information Received |
| Apr 17, 2019 | Additional Information Requested from Applicant |
| Apr 22, 2019 | HPHC Historical Preservation No Effect |
| Apr 22, 2019 | HPHC Review Pending |
| May 08, 2019 | Additional Information Received |
| May 10, 2019 | Additional Information Received |
| May 14, 2019 | Typist for Processing |
| May 14, 2019 | Biologist Report |
| May 15, 2019 | Executive Sign Off |
| May 15, 2019 | Sent to Photo Copy |
| May 15, 2019 | Permit Approved |
| Aug 06, 2019 | Land Evidence Date |
| Jun 21, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Jul 21, 2022 | Assent Requirement |