| Action Date | Action Description |
|---|---|
| Under Review/Decision | |
| Jun 12, 2019 | Assent Application Received |
| Jun 12, 2019 | Administrative Review for Completeness |
| Jun 14, 2019 | Team Review for Completeness |
| Jun 14, 2019 | Application Accepted |
| Jun 14, 2019 | Category B assigned |
| Jul 03, 2019 | HPHC Historical Preservation No Effect |
| Jul 03, 2019 | HPHC Review Pending |
| Jul 23, 2019 | 30 day Public Notice Issued |
| Jul 31, 2019 | Notice Advertisement confirmation |
| Aug 20, 2019 | Objections/Comments Received |
| Aug 23, 2019 | Public Notice End Date |
| Aug 25, 2019 | Letter of Support for Project |
| Sep 20, 2019 | Public Hearing Notices Mailed |
| Sep 25, 2019 | Biologist Report |
| Sep 25, 2019 | Engineering Report |
| Sep 26, 2019 | Notice Advertisement confirmation |
| Oct 08, 2019 | Semi-Monthly Meeting Date Scheduled |
| Oct 08, 2019 | Council Approval Granted |
| Oct 08, 2019 | Public Hearing Scheduled |
| Feb 26, 2020 | Stipulation Package by Engineer |
| Feb 27, 2020 | Stipulation Package from Biologist |
| Mar 05, 2020 | Legal Response/Decision |
| Mar 09, 2020 | Executive Sign Off |
| Mar 09, 2020 | Sent to Photo Copy |
| Mar 09, 2020 | Permit Approved |
| Mar 09, 2020 | Typist for Processing |
| Apr 17, 2020 | Land Evidence Date |
| Mar 08, 2023 | US Army Corps of Engineers Approval Received |
| Nov 07, 2023 | Meeting Held |
| Dec 14, 2023 | Meeting Held |
| Feb 14, 2024 | Meeting Held |
| Feb 15, 2024 | Correspondence Mailed/Faxed/E-mailed |
| Mar 15, 2024 | Correspondence Mailed/Faxed/E-mailed |
| Apr 05, 2024 | Correspondence Received |
| Jan 02, 2025 | Monitoring Report |