| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jun 26, 2019 | Assent Application Received |
| Jun 26, 2019 | Administrative Review for Completeness |
| Jul 08, 2019 | Team Review for Completeness |
| Jul 08, 2019 | Application Accepted |
| Jul 18, 2019 | 30 day Public Notice Issued |
| Jul 24, 2019 | HPHC Review Pending |
| Jul 24, 2019 | HPHC Historical Preservation No Effect |
| Aug 18, 2019 | Public Notice End Date |
| Sep 18, 2019 | 15 day Public Notice Issued |
| Oct 03, 2019 | Public Notice End Date |
| Oct 08, 2019 | Additional Information Received |
| Nov 06, 2019 | Typist for Processing |
| Nov 06, 2019 | Executive Sign Off |
| Nov 06, 2019 | Sent to Photo Copy |
| Nov 06, 2019 | Permit Approved |
| Nov 06, 2019 | Engineering Report |
| Nov 06, 2019 | Category A* (Docks) |
| Nov 15, 2019 | US Army Corps of Engineers Approval Received |
| Dec 06, 2019 | Land Evidence Date |
| Nov 16, 2020 | Modification Request |
| Nov 18, 2020 | Administrative Review for Completeness |
| Dec 04, 2020 | Eng Team Review for Completeness |
| Dec 04, 2020 | Project Manager |
| Dec 18, 2020 | 30 day Public Notice Issued |
| Dec 23, 2020 | HPHC Review Pending |
| Dec 23, 2020 | HPHC Historical Preservation No Effect |
| Jan 18, 2021 | Public Notice End Date |
| Jan 19, 2021 | Comments Received |
| Jan 21, 2021 | US Army Corps of Engineers Approval Received |
| Mar 11, 2021 | Plans Received |
| Apr 16, 2021 | Stipulation Package by Engineer |
| Apr 16, 2021 | Engineering Report |
| Apr 19, 2021 | Typist for Processing |
| Apr 19, 2021 | Executive Sign Off |
| Apr 19, 2021 | Sent to Photo Copy |
| Apr 19, 2021 | Modification Approved |
| May 03, 2021 | Land Evidence Date |