| Action Date | Action Description |
|---|---|
| Jul 23, 2019 | Assent Application Received |
| Jul 24, 2019 | Administrative Review for Completeness |
| Jul 25, 2019 | Team Review for Completeness |
| Jul 25, 2019 | Application Accepted |
| Aug 06, 2019 | Engineering Report |
| Aug 06, 2019 | Typist for Processing |
| Aug 06, 2019 | Executive Sign Off |
| Aug 06, 2019 | Sent to Photo Copy |
| Aug 06, 2019 | Permit Approved |
| Dec 16, 2019 | HPHC Historical Preservation No Effect |
| Dec 16, 2019 | HPHC Review Pending |