| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Sep 25, 2019 | Assent Application Received |
| Sep 25, 2019 | Administrative Review for Completeness |
| Oct 09, 2019 | Eng Team Review for Completeness |
| Oct 09, 2019 | Deficient Application - Owner Notification Sent |
| May 12, 2022 | Plans Received |
| Jun 01, 2022 | Deficiency Response Received |
| Jun 08, 2022 | Eng Team Review for Completeness |
| Jun 08, 2022 | Application Accepted |
| Jun 13, 2022 | Project Manager |
| Jun 16, 2022 | 30 day Public Notice Issued |
| Jun 21, 2022 | HPHC Historical Preservation No Effect |
| Jun 21, 2022 | HPHC Review Pending |
| Jul 16, 2022 | Public Notice End Date |
| Sep 14, 2022 | Engineering Report |
| Sep 19, 2022 | Typist for Processing |
| Sep 19, 2022 | Executive Sign Off |
| Sep 19, 2022 | Sent to Photo Copy |
| Sep 19, 2022 | Permit Approved |
| Sep 19, 2022 | Permit Mailed |
| Oct 20, 2022 | Land Evidence Date |