| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Oct 07, 2019 | Assent Application Received |
| Oct 07, 2019 | Administrative Review for Completeness |
| Oct 10, 2019 | Bio Team Review for Completeness |
| Oct 10, 2019 | Application Accepted |
| Oct 29, 2019 | Additional Information Requested from Applicant |
| Nov 07, 2019 | HPHC Historical Preservation No Effect |
| Nov 07, 2019 | HPHC Review Pending |
| Dec 23, 2019 | Additional Information Received |
| Jan 17, 2020 | 30 day Public Notice Issued |
| Jan 22, 2020 | Objections/Comments Received |
| Feb 14, 2020 | Objection withdrawal received |
| Feb 17, 2020 | Public Notice End Date |
| Mar 17, 2020 | Biologist Report |
| Mar 17, 2020 | Supervisor Engineer SignOff |
| Mar 18, 2020 | Supervisor Biologist SignOff |
| Mar 19, 2020 | Executive Signoff of Staff Reports |
| Apr 17, 2020 | Ready to Schedule Semi-Monthly Meeting |
| Apr 28, 2020 | Semi-Monthly Meeting Date Scheduled |
| Apr 28, 2020 | Council Approval Granted |
| May 04, 2020 | Legal Response/Decision |
| May 21, 2020 | Typist for Processing |
| May 21, 2020 | Executive Sign Off |
| May 21, 2020 | Sent to Photo Copy |
| May 21, 2020 | Permit Approved |
| May 21, 2020 | Stipulation Package from Biologist |
| May 21, 2020 | Category A* (Docks) |
| Jun 05, 2020 | Land Evidence Date |
| Jun 12, 2020 | US Army Corps of Engineers Approval Received |