| Action Date | Action Description |
|---|---|
| Dec 06, 2019 | Bio Team Review for Completeness |
| Feb 05, 2020 | Assent Application Received |
| Feb 05, 2020 | Administrative Review for Completeness |
| Feb 14, 2020 | Eng Team Review for Completeness |
| Feb 14, 2020 | Application Accepted |
| Feb 14, 2020 | Category B assigned |
| Feb 25, 2020 | HPHC Historical Preservation No Effect |
| Feb 25, 2020 | HPHC Review Pending |
| Mar 20, 2020 | 30 day Public Notice Issued |
| Apr 20, 2020 | Public Notice End Date |
| Jun 22, 2020 | Typist for Processing |
| Jun 22, 2020 | Executive Sign Off |
| Jun 22, 2020 | Sent to Photo Copy |
| Jun 22, 2020 | Permit Approved |
| Jun 22, 2020 | Engineering Report |
| Jun 22, 2020 | Biologist Report |
| Jun 29, 2020 | Land Evidence Date |