| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Feb 20, 2020 | Assent Application Received |
| Feb 21, 2020 | Administrative Review for Completeness |
| Feb 21, 2020 | Bio Team Review for Completeness |
| Feb 21, 2020 | Application Accepted |
| Feb 21, 2020 | Category A* (Docks) |
| Feb 25, 2020 | HPHC Historical Preservation No Effect |
| Feb 25, 2020 | HPHC Review Pending |
| Feb 28, 2020 | 30 day Public Notice Issued |
| Mar 06, 2020 | Project Manager |
| Mar 29, 2020 | Public Notice End Date |
| Apr 06, 2020 | Plans Received |
| Apr 27, 2020 | Dock Meeting -- Approval |
| Apr 27, 2020 | Biologist Report |
| Apr 28, 2020 | Typist for Processing |
| Apr 28, 2020 | Permit Approved |
| Apr 28, 2020 | Executive Sign Off |
| Apr 28, 2020 | Sent to Photo Copy |
| May 26, 2020 | Land Evidence Date |
| Feb 07, 2023 | Extension of Permit Request |
| May 08, 2023 | Enforcement Compliance Inspection Required |
| May 11, 2023 | Process Extension |
| May 11, 2023 | Extension Approved |