| Action Date | Action Description |
|---|---|
| Mar 06, 2020 | Buffer Zone Management Application Received |
| Mar 10, 2020 | Administrative Review for Completeness |
| Mar 17, 2020 | Bio Team Review for Completeness |
| Mar 17, 2020 | Application Accepted |
| Mar 17, 2020 | Project Manager |
| Mar 24, 2020 | HPHC Historical Preservation No Effect |
| Mar 24, 2020 | HPHC Review Pending |
| Apr 20, 2020 | Additional Information Received |
| May 11, 2020 | Biologist Report |
| May 12, 2020 | Permit Approved |
| May 12, 2020 | Typist for Processing |
| Nov 09, 2023 | Monitoring Report |