| Action Date | Action Description |
|---|---|
| Mar 09, 2020 | Assent Application Received |
| Mar 10, 2020 | Administrative Review for Completeness |
| Mar 31, 2020 | Bio Team Review for Completeness |
| Apr 01, 2020 | Application Accepted |
| Apr 08, 2020 | HPHC Review Pending |
| Apr 08, 2020 | HPHC Historical Preservation No Effect |
| Apr 29, 2020 | Site Inspection |
| Apr 29, 2020 | Note to File |
| Apr 30, 2020 | Phone Call |
| May 01, 2020 | Correspondence Mailed/Faxed/E-mailed |
| Jul 01, 2020 | Additional Information Requested from Applicant |
| Jul 08, 2020 | Typist for Processing |
| Jul 08, 2020 | Executive Sign Off |
| Jul 08, 2020 | Sent to Photo Copy |
| Jul 08, 2020 | Permit Approved |
| Jul 08, 2020 | Biologist Report |
| Jul 13, 2020 | Land Evidence Date |
| Oct 09, 2020 | Modification Request |
| Oct 13, 2020 | Administrative Review for Completeness |
| Oct 14, 2020 | Correspondence Received |
| Oct 21, 2020 | HPHC Review Pending |
| Oct 21, 2020 | Eng Team Review for Completeness |
| Oct 21, 2020 | Bio Team Review for Completeness |
| Oct 21, 2020 | Project Manager |
| Oct 27, 2020 | HPHC Historical Preservation No Effect |
| Dec 01, 2020 | Additional Information Requested from Applicant |
| Dec 02, 2020 | Additional Information Received |
| Dec 04, 2020 | Biologist Report |
| Dec 07, 2020 | Engineering Report |
| Dec 07, 2020 | Stipulation Package from Biologist |
| Dec 07, 2020 | Stipulation Package by Engineer |
| Dec 07, 2020 | Typist for Processing |
| Dec 07, 2020 | Executive Sign Off |
| Dec 07, 2020 | Sent to Photo Copy |
| Dec 07, 2020 | Modification Approved |
| Dec 18, 2020 | Land Evidence Date |