| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jul 20, 2020 | Assent Application Received |
| Jul 20, 2020 | Administrative Review for Completeness |
| Jul 28, 2020 | Category A* (Docks) |
| Jul 28, 2020 | Bio Team Review for Completeness |
| Jul 28, 2020 | Application Accepted |
| Jul 28, 2020 | Project Manager |
| Aug 19, 2020 | HPHC Review Pending |
| Aug 19, 2020 | HPHC Historical Preservation No Effect |
| Sep 02, 2020 | Plans Received |
| Oct 15, 2020 | 30 day Public Notice Issued |
| Oct 20, 2020 | Correspondence Received |
| Nov 14, 2020 | Public Notice End Date |
| Nov 18, 2020 | Dock Meeting -- Approval |
| Nov 23, 2020 | Stipulation Package from Biologist |
| Nov 23, 2020 | Typist for Processing |
| Nov 23, 2020 | Executive Sign Off |
| Nov 23, 2020 | Sent to Photo Copy |
| Nov 23, 2020 | Permit Approved |
| Nov 23, 2020 | Biologist Report |
| Jul 01, 2021 | Land Evidence Date |