| Action Date | Action Description |
|---|---|
| Jul 21, 2020 | Maintenance Certification Request |
| Jul 23, 2020 | Administrative Review for Completeness |
| Jul 29, 2020 | Bio Team Review for Completeness |
| Jul 29, 2020 | Application Accepted |
| Aug 03, 2020 | Project Manager |
| Aug 25, 2020 | Additional Information Requested from Applicant |
| Sep 04, 2020 | HPHC Review Pending |
| Sep 04, 2020 | HPHC Historical Preservation No Effect |
| Sep 21, 2020 | Correspondence Mailed/Faxed/E-mailed |
| Oct 14, 2020 | Additional Information Received |
| Oct 19, 2020 | Biologist Report |
| Oct 20, 2020 | Permit Approved |