| Action Date | Action Description |
|---|---|
| Oct 20, 2020 | Assent Application Received |
| Oct 22, 2020 | Administrative Review for Completeness |
| Oct 22, 2020 | Eng Team Review for Completeness |
| Oct 22, 2020 | Category B assigned |
| Oct 22, 2020 | Application Accepted |
| Oct 22, 2020 | Project Manager |
| Nov 30, 2020 | Joint Public Notice |
| Dec 03, 2020 | US Army Corps of Engineers Approval Received |
| Dec 30, 2020 | Public Notice End Date |
| Jan 05, 2021 | Additional Information Received |
| Jan 21, 2021 | Additional Information Received |
| Feb 12, 2021 | Additional Information Requested from Applicant |
| Mar 17, 2021 | Additional Information Received |
| Apr 06, 2021 | Additional Information Received |
| Apr 08, 2021 | HPHC Historical Preservation No Effect |
| Apr 08, 2021 | HPHC Review Pending |
| Apr 29, 2021 | Semi-Monthly Meeting Date Scheduled |
| May 06, 2021 | Stipulation Package by Engineer |
| May 06, 2021 | Engineering Report |
| May 07, 2021 | Typist for Processing |
| May 07, 2021 | Executive Sign Off |
| May 07, 2021 | Sent to Photo Copy |
| May 07, 2021 | Permit Approved |
| May 24, 2021 | Land Evidence Date |
| Mar 07, 2024 | Extension of Permit Request |
| Mar 25, 2024 | Process Extension |
| Mar 25, 2024 | Extension Approved |