| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jan 25, 2021 | Assent Application Received |
| Jan 26, 2021 | Administrative Review for Completeness |
| Feb 01, 2021 | Category A* (Docks) |
| Feb 01, 2021 | Bio Team Review for Completeness |
| Feb 01, 2021 | Application Accepted |
| Feb 01, 2021 | Project Manager |
| Feb 05, 2021 | HPHC Review Pending |
| Feb 05, 2021 | HPHC Historical Preservation No Effect |
| Feb 09, 2021 | 30 day Public Notice Issued |
| Feb 09, 2021 | Category A* (Docks) |
| Mar 09, 2021 | Public Notice End Date |
| Mar 15, 2021 | Additional Information Requested from Applicant |
| Mar 16, 2021 | Dock Meeting -- Approval |
| Mar 16, 2021 | Additional Information Requested from Applicant |
| Apr 07, 2021 | US Army Corp of Engineers Permit Date |
| Apr 08, 2021 | Plans Received |
| Apr 21, 2021 | Stipulation Package from Biologist |
| Apr 21, 2021 | Biologist Report |
| Apr 22, 2021 | Typist for Processing |
| Apr 22, 2021 | Executive Sign Off |
| Apr 22, 2021 | Sent to Photo Copy |
| Apr 22, 2021 | Permit Approved |
| Apr 29, 2021 | Land Evidence Date |