| Action Date | Action Description |
|---|---|
| Feb 11, 2021 | Freshwater Wetland - Preliminary Determination |
| Feb 15, 2021 | Administrative Review for Completeness |
| Feb 22, 2021 | Deficiency Response Received |
| Mar 01, 2021 | Deficient Application - Owner Notification Sent |
| Mar 01, 2021 | Note to File |
| Mar 02, 2021 | Category A assigned |
| Mar 02, 2021 | Phone Call |
| Mar 26, 2021 | Additional Information Received |
| Mar 30, 2021 | Application Accepted |
| Mar 30, 2021 | Bio Team Review for Completeness |
| Mar 31, 2021 | Project Manager |
| Apr 13, 2021 | HPHC Historical Preservation No Effect |
| Apr 13, 2021 | HPHC Review Pending |
| Apr 27, 2021 | Additional Information Requested from Applicant |
| Apr 28, 2021 | Correspondence Received |
| Apr 29, 2021 | Stipulation Package from Biologist |
| Apr 29, 2021 | Biologist Report |
| May 04, 2021 | Typist for Processing |
| May 04, 2021 | Executive Sign Off |
| May 04, 2021 | Sent to Photo Copy |
| May 04, 2021 | Permit Approved |
| May 12, 2021 | Land Evidence Date |