| Action Date | Action Description |
|---|---|
| HPHC Review Pending | |
| Mar 11, 2021 | Maintenance Certification Request |
| Mar 11, 2021 | Administrative Review for Completeness |
| Mar 15, 2021 | Bio Team Review for Completeness |
| Mar 15, 2021 | Biologist Report |
| Mar 15, 2021 | Stipulation Package from Biologist |
| Mar 15, 2021 | Permit Approved |
| Mar 15, 2021 | Typist for Processing |
| Mar 15, 2021 | Typist for Processing |
| Mar 15, 2021 | Executive Sign Off |
| Mar 15, 2021 | Sent to Photo Copy |
| Mar 15, 2021 | Application Accepted |
| Mar 24, 2021 | Land Evidence Date |