| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Mar 18, 2021 | Assent Application Received |
| Mar 24, 2021 | Administrative Review for Completeness |
| Mar 24, 2021 | Additional Information Requested from Applicant |
| Mar 24, 2021 | Plans Received |
| Mar 29, 2021 | Plans Received |
| Mar 30, 2021 | Application Accepted |
| Mar 30, 2021 | Bio Team Review for Completeness |
| Mar 31, 2021 | Project Manager |
| Mar 31, 2021 | Category A* (Docks) |
| Apr 13, 2021 | HPHC Review Pending |
| Apr 13, 2021 | HPHC Historical Preservation No Effect |
| Apr 16, 2021 | 30 day Public Notice Issued |
| May 17, 2021 | Public Notice End Date |
| May 20, 2021 | US Army Corp of Engineers Permit Date |
| Jun 17, 2021 | Dock Meeting -- Approval |
| Jun 18, 2021 | Biologist Report |
| Jun 22, 2021 | Stipulation Package from Biologist |
| Jun 22, 2021 | Typist for Processing |
| Jun 22, 2021 | Executive Sign Off |
| Jun 22, 2021 | Sent to Photo Copy |
| Jun 22, 2021 | Permit Approved |
| Aug 23, 2021 | Land Evidence Date |