| Action Date | Action Description |
|---|---|
| Mar 30, 2021 | Assent Application Received |
| Mar 31, 2021 | Administrative Review for Completeness |
| Mar 31, 2021 | CHA Worksheet received |
| Apr 01, 2021 | Additional Information Requested from Applicant |
| Apr 05, 2021 | Additional Information Received |
| Apr 05, 2021 | Application Accepted |
| Apr 05, 2021 | Project Manager |
| Apr 05, 2021 | Bio Team Review for Completeness |
| May 18, 2021 | Note to File |
| May 19, 2021 | HPHC Historical Preservation No Effect |
| May 19, 2021 | HPHC Review Pending |
| May 21, 2021 | Biologist Report |
| May 21, 2021 | Stipulation Package from Biologist |
| May 24, 2021 | Typist for Processing |
| May 24, 2021 | Executive Sign Off |
| May 24, 2021 | Sent to Photo Copy |
| May 24, 2021 | Permit Approved |
| Jun 15, 2021 | Land Evidence Date |
| Jul 07, 2021 | Modification Request |
| Jul 09, 2021 | Administrative Review for Completeness |
| Jul 09, 2021 | CHA Worksheet received |
| Jul 13, 2021 | Bio Team Review for Completeness |
| Aug 05, 2021 | HPHC Historical Preservation No Effect |
| Aug 05, 2021 | HPHC Review Pending |
| Aug 27, 2021 | Additional Information Requested from Applicant |
| Aug 30, 2021 | Correspondence Mailed/Faxed/E-mailed |
| Aug 31, 2021 | Plans Received |
| Sep 07, 2021 | Additional Information Requested from Applicant |
| Sep 07, 2021 | Additional Information Received |
| Sep 07, 2021 | Biologist Report |
| Sep 10, 2021 | Typist for Processing |
| Sep 13, 2021 | Executive Sign Off |
| Sep 13, 2021 | Sent to Photo Copy |
| Sep 13, 2021 | Modification Approved |
| Nov 05, 2021 | Duplicate Original Assent requested/mailed |
| Nov 12, 2021 | Land Evidence Date |