| Action Date | Action Description |
|---|---|
| Apr 27, 2021 | Assent Application Received |
| May 03, 2021 | Administrative Review for Completeness |
| May 27, 2021 | Bio Team Review for Completeness |
| May 27, 2021 | Application Accepted |
| May 28, 2021 | Project Manager |
| Jun 02, 2021 | Additional Information Received |
| Jun 02, 2021 | CHA Worksheet received |
| Jun 14, 2021 | HPHC Review Pending |
| Jun 14, 2021 | HPHC Historical Preservation No Effect |
| Dec 06, 2021 | Plans Received |
| Jan 20, 2022 | Additional Information Received |
| Mar 25, 2022 | Additional Information Received |
| May 02, 2022 | Additional Information Received |
| May 25, 2022 | Biologist Report |
| Jun 01, 2022 | Permit Mailed |
| Jun 01, 2022 | Typist for Processing |
| Jun 01, 2022 | Executive Sign Off |
| Jun 01, 2022 | Sent to Photo Copy |
| Jun 01, 2022 | Permit Approved |
| Jun 03, 2022 | Permit Mailed |
| Jun 06, 2022 | Land Evidence Date |
| Mar 28, 2025 | Extension of Permit Request |
| Apr 04, 2025 | Enforcement Compliance Inspection Required |
| Apr 04, 2025 | Process Extension |
| Apr 04, 2025 | Extension Approved |