| Action Date | Action Description |
|---|---|
| May 03, 2021 | Assent Application Received |
| May 10, 2021 | Administrative Review for Completeness |
| May 11, 2021 | Bio Team Review for Completeness |
| May 11, 2021 | Application Accepted |
| May 11, 2021 | Project Manager |
| Jun 08, 2021 | HPHC Historical Preservation No Effect |
| Jun 08, 2021 | HPHC Review Pending |
| Jun 09, 2021 | Additional Information Received |
| Jun 16, 2021 | Additional Information Received |
| Jun 16, 2021 | Stipulation Package from Biologist |
| Jun 16, 2021 | Biologist Report |
| Jun 21, 2021 | Typist for Processing |
| Jun 21, 2021 | Executive Sign Off |
| Jun 21, 2021 | Permit Approved |
| Aug 31, 2021 | Duplicate Original Assent requested/mailed |
| Aug 31, 2021 | Permit Mailed |
| Sep 20, 2021 | Land Evidence Date |