| Action Date | Action Description |
|---|---|
| Aug 02, 2021 | Assent Application Received |
| Aug 06, 2021 | Administrative Review for Completeness |
| Aug 06, 2021 | CHA Worksheet received |
| Aug 18, 2021 | Bio Team Review for Completeness |
| Aug 18, 2021 | Application Accepted |
| Aug 19, 2021 | Project Manager |
| Sep 16, 2021 | HPHC Review Pending |
| Sep 16, 2021 | HPHC Historical Preservation No Effect |
| Nov 16, 2021 | Plans Received |
| Nov 18, 2021 | Plans Received |
| Dec 06, 2021 | Additional Information Received |
| Dec 21, 2021 | Objections/Comments Received |
| Jan 10, 2022 | Comments Received |
| Jan 11, 2022 | Letter of Support for Project |
| Jan 12, 2022 | Additional Information Received |
| May 24, 2022 | Letter of Support for Project |
| May 25, 2022 | Letter of Support for Project |
| May 27, 2022 | Letter of Support for Project |
| Aug 05, 2022 | Ready to Schedule Semi-Monthly Meeting |
| Aug 05, 2022 | Mail Agenda Notice |
| Aug 18, 2022 | Biologist Report |
| Aug 23, 2022 | Council Approval Granted |
| Aug 23, 2022 | Semi-Monthly Meeting Date Scheduled |
| Aug 29, 2022 | Plans Received |
| Aug 30, 2022 | Plans Received |
| Sep 28, 2022 | 30 Day Appeal Notification to Owner |
| Sep 28, 2022 | Legal Response/Decision |
| Oct 04, 2022 | Stipulation Package from Biologist |
| Oct 05, 2022 | Permit Mailed |
| Oct 05, 2022 | Typist for Processing |
| Oct 05, 2022 | Executive Sign Off |
| Oct 05, 2022 | Sent to Photo Copy |
| Oct 05, 2022 | Permit Approved |
| Oct 11, 2022 | Permit Mailed |
| Oct 24, 2022 | Land Evidence Date |