| Action Date | Action Description |
|---|---|
| Aug 16, 2021 | Assent Application Received |
| Aug 17, 2021 | Administrative Review for Completeness |
| Aug 17, 2021 | CHA Worksheet received |
| Aug 19, 2021 | Additional Information Requested from Applicant |
| Sep 02, 2021 | Additional Information Requested from Applicant |
| Sep 02, 2021 | Additional Information Received |
| Sep 10, 2021 | Application Accepted |
| Sep 10, 2021 | Project Manager |
| Sep 10, 2021 | Bio Team Review for Completeness |
| Oct 26, 2021 | HPHC Review Pending |
| Oct 26, 2021 | HPHC Historical Preservation No Effect |
| Oct 28, 2021 | Biologist Report |
| Nov 03, 2021 | Typist for Processing |
| Nov 03, 2021 | Executive Sign Off |
| Nov 03, 2021 | Sent to Photo Copy |
| Nov 03, 2021 | Permit Approved |
| Nov 08, 2021 | Permit Mailed |
| Aug 08, 2022 | Land Evidence Date |