| Action Date | Action Description |
|---|---|
| Oct 21, 2021 | Assent Application Received |
| Feb 07, 2022 | Administrative Review for Completeness |
| Feb 07, 2022 | Deficient Application - Owner Notification Sent |
| Feb 16, 2022 | Deficient Application Picked Up |
| Mar 11, 2022 | Deficiency Response Received |
| Mar 21, 2022 | Bio Team Review for Completeness |
| Mar 21, 2022 | Deficient Application - Owner Notification Sent |
| Jun 06, 2022 | Deficiency Response Received |
| Jun 10, 2022 | Bio Team Review for Completeness |
| Jun 10, 2022 | Application Accepted |
| Jun 13, 2022 | Project Manager |
| Jul 07, 2022 | HPHC Review Pending |
| Jul 07, 2022 | HPHC Historical Preservation No Effect |
| Jul 11, 2022 | Additional Information Requested from Applicant |
| Jul 18, 2022 | Correspondence Received |
| Jul 22, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Sep 23, 2022 | Phone Call |
| Oct 05, 2022 | Additional Information Received |
| Oct 17, 2022 | Additional Information Received |
| Oct 20, 2022 | Additional Information Received |
| Oct 21, 2022 | Correspondence Received |
| Oct 21, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Oct 24, 2022 | Correspondence Received |
| Oct 31, 2022 | Correspondence Received |
| Nov 21, 2022 | Additional Information Requested from Applicant |
| Nov 29, 2022 | Phone Call |
| Nov 29, 2022 | Biologist Report |
| Nov 30, 2022 | Typist for Processing |
| Nov 30, 2022 | Executive Sign Off |
| Nov 30, 2022 | Sent to Photo Copy |
| Nov 30, 2022 | Permit Approved |
| Dec 01, 2022 | Permit Mailed |
| Dec 05, 2022 | Land Evidence Date |
| Mar 08, 2023 | Commencement of Work Notice received |