| Action Date | Action Description |
|---|---|
| Mar 01, 2022 | Assent Application Received |
| Mar 07, 2022 | Administrative Review for Completeness |
| Mar 07, 2022 | Bio Team Review for Completeness |
| Mar 07, 2022 | Application Accepted |
| Mar 07, 2022 | Project Manager |
| Apr 01, 2022 | HPHC Historical Preservation No Effect |
| Apr 01, 2022 | HPHC Review Pending |
| Apr 22, 2022 | Additional Information Requested from Applicant |
| May 24, 2022 | Additional Information Received |
| May 24, 2022 | Biologist Report |
| May 24, 2022 | Additional Information Received |
| Jun 07, 2022 | Note to File |
| Jun 07, 2022 | Additional Information Requested from Applicant |
| Aug 25, 2022 | Correspondence Received |
| Aug 26, 2022 | Permit Approved |
| Aug 26, 2022 | Typist for Processing |
| Aug 26, 2022 | Executive Sign Off |
| Aug 26, 2022 | Sent to Photo Copy |
| Aug 30, 2022 | Permit Mailed |
| Jan 12, 2023 | Land Evidence Date |